You are here: Projects/Current Projects / Santa Rosa Memorial Hospital Central Processing Renovations

Santa Rosa Memorial Hospital Central Processing Renovations

Project Team: TLCD Architecture, NM&R Architects, Eclipse Mechanical Engineers

Visit Website

Project Manager: Josh Grigg
Estimator: Rick Grossmann
Superintendent: Scott Thomas

Project description:  Sink and Washer Replacement including replacing Steris Caviwave Ultrasonic Cleaner.

Site constraints:   Multi-phased project to allow area to remain operational at all times, coordination of temporary infection control barrier that can be taken down after the end of the 8 hour shift and the wall cavity re-installed until the next shift can begin.